Yesterday, Capital Metro received notification from the Federal Railroad Administration (FRA) and the Texas Department of Transportation (TxDOT) of allegations issued against our rail contractor Veolia Transportation. The allegations are in reference to incidents in February where two Veolia rail supervisors operating MetroRail trains entered a section of track without prior authorization during system testing.
Veolia is investigating this matter thoroughly and working with the FRA and TxDOT to address this issue.
Based on this incident and additional issues identified during rail testing over the past several weeks, Capital Metro will allow more time for Veolia to complete the training of engineers and dispatchers and additional testing of the rail line. Capital Metro is working with Veolia to establish a revised timeline for the start of service initially planned for Monday, March 30.
The ribbon-cutting communitywide celebration of MetroRail on Saturday, March 28, will move forward as planned. Learn more about the event on our Web site.
Veolia Transportation issued a statement about the FRA allegations. Read the statement here.